Cosco's big foreign client to delay payments?

Cosco susceptible for credit risk as other customers may also negotiate for more back-ended payment schedules.

Here's from OCBC Investment Research:

According to Sevan Drilling, the payment terms of Sevan Drilling Rig 4 contracted with COSCO Shipyard has been changed to a more back- ended schedule, i.e. 5% on contract execution in May 2011, 5% around Mar 2012, and the balance of 90% on delivery in 2Q12.

The original schedule was 5% on contract execution, 15% prior to steel cutting and balance 80% on delivery. (We checked with COSCO yesterday, but the group was unable to confirm this.)

Similarly, other customers may also negotiate for more back-ended payment schedules. This would mean that COSCO’s credit risk (and possibility fx/cashflow risk) may be higher than expected.

Join Singapore Business Review community
Join Singapore Business Review community
A NOTE FROM SINGAPORE BUSINESS REVIEW

Reaching the people who run Asia's businesses is harder than it used to be.

Inboxes are crowded. Attention is short. The executives you most want to reach — the founders, CFOs, and operators who actually move budgets — are the hardest to find through the usual channels. If you're building a company, a category, or a reputation, you already know this.

We've spent twenty years building the room they read. Singapore Business Review is where senior decision makers in Singapore and across Southeast Asia come for business coverage they can't get elsewhere — in print, online, and in person at the summits and roundtables we host across seven markets.

If you have something these readers should know about — a point of view worth publishing, a product worth their attention, an event worth their time — we'd like to hear what you're trying to do.

Top News

High-spec facilities to drive industrial demand
Realion expects rents to rise by up to 3% in 2027 despite the completion of 12.3 million sq ft of new space.
Commercial Property