Singapore ranks fourth globally for data centre construction costs

It also led SEA at $20.20 per watt, ahead of Jakarta and Kuala Lumpur.

Singapore ranked as the fourth most expensive market globally in terms of data centre construction costs, according to research from Turner & Townsend.

Singapore also led construction costs in SEA at $20.20 per watt (US$15.39), well ahead of Jakarta at $15.70/W (US$11.96), which ranked 26th globally.

Kuala Lumpur and Johor Bahru ranked 49th and 50th, respectively, both at $13.20/W (US$10.06).

Bangkok, at $12.68/W (US$9.67), placed 55th, whilst Manila followed in 56th at $12.52/W (US$9.55).

Meanwhile, Ho Chi Minh City emerged as SEA’s most cost-competitive market, ranking 60th at $10.90/W (US$8.32).

Turner & Townsend said the cost spread reflects the different stages of market maturity across the region.

“The common theme is that wherever the project sits, power, land and skilled people are in high demand,” said Patrick Thilagaraj, project director for data centres at Turner & Townsend Malaysia.

“As Southeast Asia’s data centre market continues to scale, understanding these cost dynamics will be critical for developers and investors planning their next move in the region,” he added.

Despite some stabilisation in cost pressures, Turner & Townsend said structurally higher construction costs and risks are increasingly priced into contracting, whilst a deepening skills shortage is putting pressure on labour costs.

The rising costs of data centre construction are driven by the growing scale of the projects, particularly for artificial intelligence facilities, which require alternative delivery approaches and technical specialists to overcome strained capacity, the firm added.

The index covered more than 500 live or recently completed projects across 62 markets, with construction costs benchmarked against a typical 60-megawatt data centre design.

$1 = US$0.76

Join Singapore Business Review community

Follow the link for more news on

Join Singapore Business Review community
A NOTE FROM SINGAPORE BUSINESS REVIEW

If you've been wondering whether SBR could work for your company — yes, probably.

A lot of the companies we partner with started as readers. They'd been following our coverage for a while, saw their own customers and competitors in it, and eventually asked the obvious question: could we do something with you? The answer is usually yes. The shape of it depends on what you're trying to do.


The options are broader than most people assume — thought leadership articles, sponsored content, industry summits across Southeast Asia, regional awards programmes, podcasts, and media placements in print and digital. Some partners use one channel; most use a mix. We figure out the right combination by starting with your brief, not with our rate card.


So if the question has been on your mind, here's the easy way to ask it.

We'll tell you honestly whether we can help, and how. It's a better use of everyone's time.